Be Prepared: Managing Environmental Inspections

Is your shop ready for an environmental inspection? Preparation and documentation can help minimize your facility’s risk of noncompliance.

Ethan R. Ware, Esquire, Williams Mullen

Share

Q: My facility takes environmental regulations very seriously. What advice do you have for working with inspectors?

Violations identified during an inspection can result in significant penalties and costs. Fines for a single violation of hazardous waste container requirements may be as high as $54,000 per day per container, and often, EPA requires “mitigation” costs to be paid to minority neighborhoods for any environmental impacts. While inspections cannot be prevented, it is important for surface finishers to manage the inspection within legal guidelines.     

Scope of inspections

Surface finishers diligently guard against environmental impacts. Air emissions are monitored and minimized; wastewater is treated in multi-million-dollar treatment systems to meet categorical and water quality-based effluent limits; and solid wastes are subject to stringent container management requirements including labeling, inspection and recordkeeping provisions.

In 2015, EPA promulgated guidance on how regulators should inspect facilities for compliance with environmental regulations. The guidance allows for “Full Compliance” or “Partial Compliance” inspections: the former involves a complete review of monitoring systems, recordkeeping and compliance for a specific regulatory program, while the latter focuses on regulatory requirements for a specific piece of equipment or process.

Inspections may be triggered by schedule or due to complaints. For example, most surface finishers are large quantity generators (LQG) of hazardous waste and the guidance directs EPA to inspect at least six LQGs in each state annually and the state to inspect 20% of the LQGs during the same calendar year. Complaints (anonymous or named) require inspection unless it is duplicative. Facilities located near areas designated “environmental justice concerns” will be targeted by EPA during the next 4 years; these are areas where EPA believes pollution from a facility has a “disparate impact” on populations or subpopulations of race, national origin, religion or “socioeconomic” levels.

Managing the inspection

The keys to managing any inspection are preparation and documentation.  Each may minimize a facility’s risk of significant noncompliance and reduce penalties if noncompliance is discovered.

Every electroplating business should develop a pre-inspection plan. A pre-inspection packet should include a guest log-in sheet/identification procedures, copying services, camera or video device, sampling equipment for solid waste and wastewater, and PPE requirements list. The facility should require inspectors to show identification and any HAZWOPER (Hazardous Waste Operations and Emergency Response) certifications. The proper person should be onsite during the inspection; if they cannot be there, explain the inspection will not be complete without them and request it be delayed until they can arrive. Prior to initiating the inspection, ask what the inspector is there to see: this is important in order to lock down the exact scope of the inspection. Key EHS personnel should be trained on the pre-inspection process.

Managing the inspection itself is equally important. Take the inspector or inspection team to see the areas requested during the pre-inspection meeting — and only those areas. Do not leave the inspector during the inspection and make sure to duplicate any photographs taken by the inspector, and split samples. This information may be useful for contested citations. 

Finally, wrap up the inspection with a post-inspection meeting. This is the most important part of the process. It gives the facility an opportunity to minimize the scope of violations. Ask the inspectors what, if any, violations they observed. The answers will be helpful later if new or different claims are made by the inspectors during an enforcement process.

Conclusion

EPA and States have broad authority to perform inspections. EPA guidance sets boundaries for the inspections, but industries should understand the purpose of all inspections is to accumulate evidence of non-compliance. Companies can prepare in advance to minimize the scope of inspections by developing Pre-Inspection Plans (including collecting necessary tools for the inspection), managing the actual site visit, and asking the inspectors what, if any, violations they observed. All companies, including surface finishers, can reduce the chances of a “runaway” inspection by careful planning.

About the Author

 
environmental law

Ethan Ware

Ethan is a partner at law firm Williams Mullen. He represents businesses and industries in environmental and health and safety legal matters. Visit williamsmullen.com.

Luster-On Products
Reduced Ion Electroless Nickel
In-Place Repairs for Canning Presses
Hitachi High-Tech FT200 series
Rectifiers for the Plating Industry
KCH Engineered Systems
FISCHERSCOPE® XAN® LIQUID ANALYZER
Pretreatment Washer and Finishing Equipment

Related Content

Electroplating

Advantages to Pumped Eductor Agitation

Not all agitation methods are created equally. Pumped agitation with eductor nozzles can improve process tanks and quickly show a reduction in operating costs while keeping staff safe, following environmental legislation and preventing pollution.

Read More
Electroplating

How to Choose Between Sulfate and Chloride-Based Trivalent Chromium

There are several factors to consider when choosing between sulfate and chloride-based baths for trivalent chromium plating. Mark Schario of Columbia Chemical discusses the differences and what platers should keep in mind when evaluating options.

Read More
basics

An Overview of Electroless Nickel Plating

By definition, electroless plating is metal deposition by a controlled chemical reaction.

Read More
Electroplating

Innovation in Plating on Plastic

Plating on advanced plastics solution offers improved adhesion, temperature resistance and cost savings.

Read More

Read Next

Sponsored

Delivering Increased Benefits to Greenhouse Films

Baystar's Borstar technology is helping customers deliver better, more reliable production methods to greenhouse agriculture.

Read More
Parts Cleaning

Education Bringing Cleaning to Machining

Debuting new speakers and cleaning technology content during this half-day workshop co-located with IMTS 2024.

Read More
Parts Cleaning

A ‘Clean’ Agenda Offers Unique Presentations in Chicago

The 2024 Parts Cleaning Conference, co-located with the International Manufacturing Technology Show, includes presentations by several speakers who are new to the conference and topics that have not been covered in past editions of this event.   

Read More
Reduced Ion Electroless Nickel